Date | Topic | Document |
October 14, 2022 | Mothers for Peace and Friends of the Earth filed a joint reply to the CPUC regarding PG&E comments on a scoping memo and ruling. | https://mothersforpeace.org/economic-and-safety-issues-at-diablo-canyon-put-californians-on-a-slippery-slope/ |
November 17, 2022 | Mothers for Peace, Friends of the Earth, Environmental Working Group and Committee to Bridge the Gap submitted a letter to the NRC Commissioners objecting to PG&E’s requests related to withdrawn license renewal application for Diablo Canyon. | https://mothersforpeace.org/wp-content/uploads/2022/11/2022.11.17-Organizations-letter-to-NRC-re-Diablo-Canyon-license-renewal-.pdf |
December 6, 2022 | Mothers for Peace, Friends of the Earth, Environmental Working Group and Committee to Bridge the Gap submitted a letter to the NRC Commissioners insisting that PG&E must be required to submit a new license renewal application for Diablo Canyon and that NRC must comply with all safety and environmental requirements. | https://mothersforpeace.org/wp-content/uploads/2022/12/2022.12.06-Organizations-letter-to-NRC-re-PGE-exemption-request-.pdf |
January 10, 2023 | Mothers for Peace, Friends of the Earth, and Environmental Working Group filed a petition asserting that the NRC does not have legal authority to extend Diablo Canyon’s operating licenses past its scheduled shutdown dates of 2024 and 2025. | https://mothersforpeace.org/wp-content/uploads/2023/01/2023.01.10-SLOMFP-FoE-EWG-Petition-re-Diablo-Canyon.pdf |
February 13, 2023 | Mothers for Peace, Friends of the Earth, and the Environmental Working Group filed a petition demanding that the NRC finish its legal obligation to keep Diablo Canyon on schedule to close in 2024 and 2025. | https://mothersforpeace.org/wp-content/uploads/2023/02/2023.02.13-Organizations-Letter-to-NRC-re-Diablo-Canyon.pdf |
March 13, 2023 | Mothers for Peace petitioned the NRC for a hearing regarding PG&E’s application to renew the license for its spent fuel storage facility. | https://mothersforpeace.org/wp-content/uploads/2023/03/2023.03.13-SLOMFP-Hearing-Request-re-DC-ISFSI.pdf |
March 17, 2023 | Mothers for Peace, Friends of the Earth, and Environmental Working Group filed comments objecting to a proposal by the California Water Resources Control Board to extend by five years deadlines by which PG&E must comply with the Clean Water Act by requiring the replacement of its once-through cooling system with a closed-cycle system. | https://mothersforpeace.org/wp-content/uploads/2023/03/20230317_Comments-on-Water-Board-Policy_Final.pdf |
March 28, 2023 | Mothers for Peace, Friends of the Earth, and Environmental Working Group submitted a letter to the NRC demanding that the Commissioners reverse their staff’s decision to exempt PG&E from the NRC’s timely renewal regulation. | https://mothersforpeace.org/wp-content/uploads/2023/03/2023.03.28-Organizations-Letter-to-NRC-Comms-re-Diablo-Canyon.pdf |
April 28, 2023 | Mothers for Peace, Friends of the Earth, and Environmental Working Group filed a petition with the Ninth Circuit U.S. Court of Appeals challenging the NRC’s unprecedented decision to grant PG&E an exemption from submitting a license renewal application for Diablo Canyon. | https://mothersforpeace.org/wp-content/uploads/2023/05/2023.04.28-SLOFMP-FoE-EWG-Petition-for-Review-final.pdf |
June 30, 2023 | Mothers for Peace, Friends of the Earth, and Environmental Working Group Challenge Diablo Canyon License Renewal in the Ninth Circuit Court of Appeals. | https://mothersforpeace.org/wp-content/uploads/2023/07/2023.06.30-Petitioners-Opening-Brief.pdf |
June 30, 2023 | Mothers for Peace submitted testimony with the CPUC. | Attorney Sabrina Venskus: https://mothersforpeace.org/wp-content/uploads/2023/07/OVC_SLOMFP.pdf Peter Bradford: https://mothersforpeace.org/wp-content/uploads/2023/07/Peter-Bradford-Testimony_Final.1.pdf Samuel Miranda: https://mothersforpeace.org/wp-content/uploads/2023/07/Samuel-Miranda-Testimony_Final.1.pdf Dr. Peter Bird: https://mothersforpeace.org/wp-content/uploads/2024/08/Opening-Testimony-of-Dr.-Peter-Bird.pdf Rao Konidena: https://mothersforpeace.org/wp-content/uploads/2023/07/Rao-Konidena-Testimony_Final.1.pdf Dr. Mark Cooper: https://mothersforpeace.org/wp-content/uploads/2023/07/20230710_Corrected_OT_Cooper_A.pdf |
September 14, 2023 | Mothers for Peace and Friends of the Earth demand an immediate shutdown of Diablo Canyon’s Unit 1 and a hearing to address the decades-long delay in inspecting and testing pressure vessel. | https://mothersforpeace.org/wp-content/uploads/2023/09/2023.09.14-FINAL-SLOMFP-FoE-Request-CORRECTED-EVENING-2023.09.14.pdf |
November 30, 2023 | Mothers for Peace and Friends of the Earth Sue the NRC over Denying Hearing on Delayed Diablo Canyon Inspections (embrittlement of Unit 1). | https://mothersforpeace.org/november-30-2023-mothers-for-peace-and-friends-of-the-earth-sue-the-nrc-over-denying-hearing-on-delayed-diablo-canyon-inspections/ |
December 14, 2023 | Mothers for Peace published a briefing paper for the citizens of California, the Legislature, and the Governor on important new data and analyses since the passage of SB 846. | https://mothersforpeace.org/wp-content/uploads/2023/12/2023.12.14-SLOMFP-Briefing-Paper.pdf |
March 4, 2024 | Mothers for Peace, Friends of the Earth, and Environmental Working Group file to intervene in the Diablo Canyon relicensing process. | https://mothersforpeace.org/march-4-2024-mothers-for-peace-friends-of-the-earth-and-environmental-working-group-file-to-intervene-in-the-diablo-canyon-relicensing-process/ |
March 20, 2024 | Mothers for Peace and Friends of the Earth Filed Federal Court Appeal which Challenges NRC’s Oversight of Safety Condition in Diablo Canyon Unit 1 (embrittlement of Unit 1). | https://mothersforpeace.org/wp-content/uploads/2024/03/2024.03.20-Pets-Opening-Brief-no-addendum.pdf |
June 27, 2024 | Request Filed by Mothers for Peace, Friends of the Earth, and Environmental Working Group for a Rehearing in the U.S. 9th Circuit Court of Appeals. | https://mothersforpeace.org/wp-content/uploads/2024/06/2024.06.27-Petition-for-Rehearing-No.-23-852.pdf |
July 3, 2024 | NRC Memo and Order Denying Request for Hearing and Terminating Proceeding | https://mothersforpeace.org/wp-content/uploads/2024/07/2024.07.03-Memo-and-Order-Denying-Request-for-Hearing-and-Terminating-Proceeding-1.pdf |
July 29, 2024 | Mothers for Peace, Friends of the Earth, and Environmental Working Group Filed an Appeal with the NRC regarding denial of a public hearing in license renewal | https://mothersforpeace.org/wp-content/uploads/2024/07/2024.07.29-PETS.-BRIEF-ON-APPEAL-OF-LBP-24-06.pdf |
July 29, 2024 | Mothers for Peace filed testimony in the 2nd phase of the CPUC proceeding. | Rao Konidena: https://mothersforpeace.org/wp-content/uploads/2024/08/Corrected-Opening-Testimony-of-Rao-Konidena_PUB.pdf Peter Bradford: https://mothersforpeace.org/wp-content/uploads/2024/08/Opening-Testimony-of-Peter-Bradford-.pdf Dr. Mark Cooper: https://mothersforpeace.org/wp-content/uploads/2024/08/Opening-Testimony-of-Mark-Cooper-1.pdf Dr. Peter Bird: https://mothersforpeace.org/wp-content/uploads/2024/08/Opening-Testimony-of-Dr.-Peter-Bird.pdf Dr. Digby Macdonald: https://mothersforpeace.org/wp-content/uploads/2024/08/Opening-Testimony-of-Digby-Macdonald.pdf |
August 5, 2024 | The NRC denied request for a rehearing in the ninth Circuit Court of Appeals challenging the NRC’s unprecedented decision to grant PG&E an exemption from submitting a license renewal application for Diablo Canyon. | https://mothersforpeace.org/wp-content/uploads/2024/08/2024.08.05-Order-Denying-Rehearing-and-Rehearing-En-Banc.pdf |
Oct 1, 2024 | Mothers for Peace filed an Opening Brief with the CPUC in the 2nd phase of the proceeding. | https://mothersforpeace.org/wp-content/uploads/2024/10/20241001_Opening-Brief-of-SLOMFP_FNL.pdf |
Oct 21, 2024 | Mothers for Peace filed a Reply Brief with the CPUC in the 2nd phase of the proceeding. | https://mothersforpeace.org/wp-content/uploads/2024/10/A2403018_SLOMFP-Reply-Brief_Final.pdf |
Nov 4, 2024 | MFP Attorney Diane Curran appeared before the Ninth Circuit Court of Appeals in Phoenix, AZ regarding the NRC denial of a hearing request on the embrittlement of Unit 1. | Watch it: https://youtu.be/WVCPFflmVGs |